*Govt flees Council, unable to answer on Heritage–Indapur links: YSRCP*
*Police crackdown on Anganwadi workers inhuman; Govt cheating them for Two Years*
*YSRCP demands Sacking of Minister Atchannaidu over insult to Council Chairman*
*Council uproar over Tirumala laddu debate exposes govt’s fear of truth: YSRCP*
*YSRCP demands Atchamnaidu resignation*
*YS Jagan attends wedding*
YS Jagan slams crackdown on anganwadi workers
*Telangana Dy CM Bhatti Vikramarka invites YS Jagan to son’s wedding*
*Roja seeks action against BR Naidu*
*Red-Book policing replaced rule of law in AP*
Polavaram hydraulic crest gate work begins
19 Dec 2020 11:05 AM
In a key development close on the heels of Chief Minister YS Jagan Mohan Reddy’s visit to Polavaram, the Megha Engineering and Infrastructure Limited (MEIL) has launched the process of installing hydraulic crest gates for the project. As part of this work, the arms of the 48 crest gates are being installed. In the first phase, the spillway gates would be set up and the arm girders are being assembled now.
As part of this, the representatives of the MEIL and irrigation officials have performed special poojas. Later, the armed girders were linked to the 45 pillars. Speaking on the occasion Project Chief Engineer Sudhakar said that the works would be completed by May-end as per the deadline and said that the officials and the representatives of the MEIL were extending all possible help in completing the project.
Why arm girders?
Each project gate has eight arm girders and four horizontal girders. Four each girders would be set up on both sides. This constitutes the Arm Assembling. The total weight is around 31 tonnes. Thus, there are 12 girders per gate. So, for the 48 gates, there would be a total of 384 arm girders and 192 horizontal girders. Each girder is 16 meters long. After the assembling, the skin plates are installed. The arm girders will be useful in lifting the gates to the required height.